In WorkflowMax you raise a purchase order on a job (or a bulk one across several jobs) when you order from a supplier, receipt the items when they arrive, then add the supplier's bill to the purchase order. The purchase order shows Partially billed or Fully billed as bills come in, and the job shows what's on order before the invoice arrives.
What a purchase order is for
A WorkflowMax purchase order records items ordered for a job, so the job shows costs you're committed to before the supplier invoices. You can raise one for a single job, or a bulk purchase order that covers several jobs. It can include the job's cost items that haven't been ordered yet, plus anything extra.
Items are either Stock (physical goods such as building materials, which need receipting) or Service (charges such as printing or mileage).
Receipting and billing
- Issue the purchase order to the supplier.
- Receipt the items when they arrive, in full or in part. Extra cost items are added to the job when they're receipted.
- Add the bill when the supplier's invoice comes in: invoice date, due date, the supplier's invoice number, and the quantity and unit cost (before tax) of each line billed.
The first bill starts at the ordered quantities. Lower them to bill part of the order and add another bill later. The purchase order then shows Partially billed, or Fully billed once the billed quantities equal the order. Items the supplier added that weren't on the order can go on the bill as additional items.
Cancelling a bill
Open the purchase order's bills, choose the supplier invoice number, then cancel the bill and check the job cost status that will apply to its costs. The purchase order goes back to Awaiting bill or Partially billed. A bill can't be cancelled once its items have been invoiced to the client.
With an accounting integration on, one bill can't be linked to more than one purchase order, because the bill number must be unique when it syncs. If one invoice covers several jobs, use a bulk purchase order.
The double-counting trap
A purchase order's items already sit on the job as costs. If the supplier's invoice is then also added to the job as new costs, the job shows the materials twice and looks less profitable than it is. Bill the purchase order instead, so the invoice lands on the costs that are already there.
With Invoice Flow
Invoice Flow matches the purchase order number printed on a supplier invoice to your WorkflowMax purchase orders (you can also pick it from a list, or from the PDF). When it matches, Invoice Flow shows what was ordered against what's being invoiced, and flags lines that weren't on the order or cost more. When you press Send, Invoice Flow bills the purchase order in WorkflowMax instead of adding new job costs, so nothing is counted twice. Lines that weren't on the order go on the bill as additional items. WorkflowMax's own connection then sends that bill to Xero or QuickBooks, so Invoice Flow doesn't send it there as well; it finds the bill WorkflowMax sent and adds the PDF. You only ever get one bill. A matched purchase order's job may be suggested; it's never chosen for you. See Xero + WorkflowMax and QuickBooks + WorkflowMax.
Questions
Do WorkflowMax purchase orders sync to Xero?
Purchase orders themselves don't. When you add the supplier's bill to a purchase order, WorkflowMax sends that bill to Xero or QuickBooks. So don't also enter the same bill in Xero, or it's there twice.
What if the invoice is less than the purchase order?
Bill the quantities that were invoiced. The purchase order stays Partially billed until the rest arrives.
Can I bill without a purchase order?
Yes. WorkflowMax also lets you add a bill straight from a job, and Invoice Flow adds job costs as usual when there's no purchase order.